Feeds:
Posts
Comments

The grand opening!

grandopening.jpg

The building is completed on time, and Dan cuts the (banding) ribbon to open the Space of Waste to the public.

For photos of the finished building please see the Results page at the top of the screen…

Hammer time…

onsite2.jpg

The upturned carpet tiles are nailed into place on the roof

A baleful wall…

baleful-wall.jpg

The bales require a bit of persuasion to fit between the trusses

Happy ever rafter…

onsite1.jpg

The rafters prove to be more time consuming than originally thought, but eventually we get them all in place.

onsite3.jpg

We erected the timber frame in record time, using the wall panels to set out the column positions.

dsc06998.jpg

After a late night design meeting in the pub the night before a few tweaks to the design were decided upon.

dsc07013.jpg

Friday was spent manically running around getting the last components ready for the next week, but the opportunity to enjoy one last sandwich from the local bakery was not to be wasted.

dsc07038.jpg

Team Beam Bodge eventually persuaded the last frame to fit together after a quick bit of encouragement from a chisel.

Day 2: Dizzy Heights

At the start of day 2 we literally picked up where we left off. The pace of production seen the previous day continued, with the team working on the wall panels and timber frame structure simultaneously.After a minor setback with beam 2 ( I say minor, but it took the whole day to rectify), due to all components varying in width. Team ‘beam-bodge’ managed to put together beam 2 which promised to be the most challenging by far.At the same time the panel team completed their 1st panel early in the morning. It was a great achievement at the time until it began to sink in that the panel they had created was the smallest of the set!!! By the end of the day they had produced a credible number of panels. Whilst on the subject of scale, the timber frame group managed to construct all columns including the 3.5m ‘Mother’ column which reached dizzy heights.

1st of its kind     …and the next one

Tom stands prowd with the first panel. But there’s little time to admire as it’s striaght onto the next one.

clamp job 1     clamp job 2

Kevin & Peter set out the middle members of column 5 with a good example of clamping before standing back to admire

the big one pt.1     the big one pt.2

Twin towers: Sarah & Dave anchor up the 1st frame 5 column to be completed. Kevin later realises just how tall she is.

bodged beam

Team ‘Beam bodge’ finally bodge together the problematic beam 2…

all square

…and begin assembling frame 2

builders’ behind    saw-off

The day draws to an end with fun and games. Site stereotypes begin to creep into the camp while Peter & Kevin enjoy a ‘saw-off’.

Day 3: Plane-sailing

nail-forest.jpg

Day 3 was spent putting the finishing touches to timber frame elements columns, 355 finishing touches to be precise, frequently raising the question amongst the team; if the structure were to be recycled again, would it be classified as wood or metal? A neat ‘forest’ of nails is used to reinforce the beams to the engineer’s requirements.

 

 

wood-prep.jpg

Throughout the day wood was delivered, planed and shaped into accurate components to be assembled on site the following week. ‘Man-points’ were notched up left, right and centre; power tools were used wherever possible even the pencils were whittled with a Stanley knife in place of a sharpener. Dave was spotted sporting a ‘power-growl’ while planeing a particularly satisfying plank.

 

 

interest.jpg

As the day progressed news of our efforts began to reach foreign shores. Interest had reached Cardiff University, provoking an impromptu visit from travelling scholar Debbie Humble. The first of many high profile interviews was given, so the projects notoriety begins to spread.

 

 

panel-how-to-2.jpg

Panel how to:

-3 pieces of suitable material are selected and overlaid to create the desired visual effect and adequate overlap.

-Each piece is measured and cut to fit the profile of the timber frame and roof.

-A polythene membrane is stapled to the central leaf of wall panel.

-The top panel is overlaid in the correct alignment and pilot holes are drilled to locate screws.

-screws are tightened to complete the panel.

At the end of day 3:

 4 of 8 panels are complete,

12 of 12 columns are complete,

4 of 5 beams are complete,

1.5 of 3 bale wall trusses are complete.

 

In a fortnights time…

In expectation

What we expect to stand prowd on Tudor Square

The first day of construction involves construction our building components in a Womans construction college, north Sheffield.

Rapid progress was made on day one having made 8 columns and 1 1/2 beams

Construction, construction!

Despite England’s defeat in the Rugby World Cup final, Pete still finds something to cheer about as team Space of Waste arrive at the workshop.

Assembly

Jeff drills the first screws into the baby column 

 Finishing touches

Peter puts the finishing touches on column 1

Baby column

 …and there she stands for all to admire

Beam 1

Tom gets to work on beam 1 whilst Jeff looks on

Celebration 

Gordon celebrates in style as frame 1 is completed

 columnS    hardcore

The columns begin to stack up, Rosie & Ben just keep on going 

Beam team

Team ‘beam-bodge’ ponder a minor set back with beam 2

Panels

Work begins on the delicate wall panels.

making the cut

The day ends with the 1st panel half completed

Older Posts »

Follow

Get every new post delivered to your Inbox.